Factory-direct LED Dome & Spherical Displays — Shenzhen, China ✉ enquiries@luminatii.com ☎ +86 177 0402 4640
Home / LED Dome Installation

LED Dome Installation — From Site Survey to Handover

A dome is installed twice: once in the factory, where the geometry is proven, and once on site, where the building decides whether the plan survives. This page is the sequence we actually run, and the site conditions that have to be true before a crew arrives.

~180 days60 m Dome, Design to Done
8.5 kg/m²Screen Weight
≤5%Brightness Uniformity
Front + RearService Access
Before the Crew Arrives

Installation Is Decided in the Design Phase

Most site problems are design problems that were postponed. The survey, the interface drawings and the erection sequence decide whether the crew has a smooth month or a difficult one.

What we survey before quoting

An LED dome installation begins with measurements, not with a shipping date. We need the clear height to the underside of the roof, the column grid, the floor loading capacity, the door and lift dimensions, and the route a steel segment will travel from the truck to the room.

From those numbers we produce the interface drawing: where the base ring lands, where the structure ties into the building, where the power and signal cabinets sit, and how a technician reaches the top band in service. Everything after that is execution.

  • Geometry survey — clear height, footprint, column positions, floor level tolerance
  • Structural interface — base ring, roof ties, load spreading, seismic case where required
  • Power and signal — supply capacity, cabinet positions, earthing, cable routes
  • Logistics — largest segment size, lifting equipment, storage, working at height plan

How a custom dome is engineered →

Interior view of a completed LED dome steel shell ready for module installation
Sequence

The LED Dome Installation Process, Step by Step

The order below is the one we use on large domes. Changing the order is possible; changing it late is expensive.

StepWorkWho is on site
01Setting out and base preparationSurveyor, civil contractor, our engineer
02Anchor and base ring installationCivil crew under our supervision
03Steel shell erection, ring by ringSteel crew, our site supervisor, lifting contractor
04Structure survey and tolerance reportOur engineer — this gates the screen start
05Walkways, catwalks and service accessSteel crew
06Module and cabinet installation, band by bandOur installation team plus trained local crew
07Power, signal and playback commissioningOur engineers
08Calibration, first light, acceptance and trainingOur engineers, client operators
Side screen steel structure being installed inside a dome theater

Why step 04 exists

Between the steel going up and the first module going in, we measure the shell and issue a tolerance report. The connectors on our modules are XY two-way adjustable, which absorbs a real amount of accumulated tolerance — but not an unlimited amount. If the shell is outside tolerance, it is corrected before 5,300 m² of screen is hanging from it.

On the Kongtong Island project this discipline is what made a 60 m sphere close without visible seams, and it is the reason the same team can install a 5 m exhibit dome and a 60 m landmark with the same method.

Site Readiness

LED Dome Screen Installation Requirements

The checklist we issue before mobilization. If an item is not ready, the crew waits — and waiting is the most expensive thing on a dome project.

RequirementWhat we need
Clear heightThe height assumed in the design, measured and confirmed, with no unplanned services crossing the dome volume
Floor and basePrepared base or slab at the specified level, with anchor positions accessible
PowerSupply capacity matching the display load — 150 W/m² at full white peak — with earthing and protection in place
LiftingCrane, hoist or gantry rated for the largest steel segment, with a documented lift plan
AccessA route for modules and cabinets, plus working-at-height access for the installation team
StorageDry, secure space for modules and electronics before installation
EnvironmentDust and humidity control during module installation, and protection of installed bands

For a sphere, the same list applies with two additions: the suspension or base structure has to be certified for the sphere's dead load and wind case, and the content must be mapped in spherical coordinates before first light. Custom sphere installation scope →

Factory First

What Gets Proven Before Anything Ships

A dome that is only assembled on site is a dome whose problems are discovered on site. We assemble and light the bands in the factory first.

01

Band pre-assembly

Each latitude band is assembled on the factory floor to confirm the module geometry, the taper toward the pole and the seam closure before crating.

02

Full-band lighting test

Bands are lit with test patterns to check for dead pixels, color consistency and driver addressing. Faults are fixed where a replacement module is a walk away.

03

Address map and packing plan

Every module is labeled with its position, and the crates are packed in the order the site will need them. Installation follows the packing plan, not a search through boxes.

Calibration is part of installation, not a separate phase

Brightness uniformity, chroma and seam continuity are set during commissioning and verified at acceptance. The target figures on our projects are a brightness uniformity deviation within 5% and a chroma deviation within 2ΔE, at 16-bit grayscale processing and 7,680 Hz refresh.

On an acoustically transparent dome the calibration also has to account for the perforation: a 50% open area with under 5% sound transmission loss means the image is seen through the same surface the audio passes through, and the mapping has to be aligned with the audio position behind it.

LED dome calibration and mapping →  ·  Service access and maintenance →

LED dome panels being installed on a curved structure during construction
Overseas

Installing a Dome in Another Country

Most of our domes are installed outside China. The method is the same; the labor split is not.

How the crew is composed

A project engineer leads from our side and a site supervisor stays on location through the critical phases: setting out, structure alignment, the first band, module installation start, calibration and handover. Local labor handles scaffolding, rigging support and general works under that supervision.

The screen, the structure interface and the calibration stay with our team, because those three decide whether the surface closes. Civil works, scaffolding and lifting are usually better sourced locally, and we plan them with the client's contractor before mobilization.

  • Visa, insurance and working-at-height certification arranged before travel
  • Tools and spares shipped with the modules, not ordered later
  • Operator training delivered on site, in the client's working language where possible
  • Handover file with the address map, calibration record and acceptance report

How an immersive LED dome is built, from the inside →

Maintenance walkway behind an LED dome screen for service access
Handover

What Acceptance Actually Checks

A dome is accepted on measurements, not on impressions. These are the checks that close a project.

  1. Seam continuity — every band inspected for gaps and steps, with the module map verified against the design
  2. Brightness uniformity — measured across the dome, target within 5% deviation
  3. Chroma consistency — target within 2ΔE across the visible surface
  4. Refresh and grayscale — 7,680 Hz refresh, 16-bit processing, no visible scan lines on camera
  5. Content path — playback, mapping, audio sync and show control tested end to end
  6. Service access — a technician physically replaces a module from the front and from the rear route
  7. Documentation — address map, calibration record, spare list, warranty terms and training file

Acceptance is also where the operator training is signed off. A dome that is technically perfect but whose staff cannot start a show is not handed over in a usable state.

Talk to an installation engineer →  ·  See delivered projects →  ·  LED dome screen platform →

First light on a 60 m LED dome during commissioning
FAQ

Installation and Site Questions

How long does an LED dome installation take?

It depends almost entirely on the structure, not the screen. The 60 m Kongtong Island dome was completed in around 180 days from design to handover, including a steel shell, 8 lifting and openable screens, 6 mechanical doors and 10 lifting floor panels. A small exhibit dome in an existing room is measured in weeks, not months.

Do you send engineers to install on site?

Yes. Our engineers supervise erection and commissioning on site, and we work alongside the client's local contractor for civil works, scaffolding and lifting. The display, the structure interface and the calibration stay with our team, because those three determine whether the dome closes without seams.

What does the building need to provide before installation?

A level or properly prepared base, the clear height the design assumes, a power supply sized to the display load, a lifting plan for the largest steel segment, a secure storage area and a route for modules to reach the dome. We issue a site readiness checklist before mobilization so nothing is discovered on arrival.

Do you pre-assemble the dome in the factory?

Yes. Bands are pre-assembled and lit in the factory to verify geometry, module mapping and driver addressing before shipment. Factory pre-assembly is what makes a curved surface predictable on site — problems are found where they are cheap to fix.

How is the installation checked before handover?

Acceptance covers brightness uniformity within 5%, chroma deviation within 2ΔE, seam continuity across every band, refresh at 7,680 Hz, grayscale at 16-bit, the full content playback path, and a documented module-by-module address map. All of it is recorded and handed over with the training file.

Can you install a dome into an operating building?

Yes, with a phasing plan. Museums, malls and parks rarely close for a dome. We sequence the work around opening hours, isolate dust and noise, and plan the heavy lifts for closed periods.

How are overseas installations handled?

One project engineer leads from our side, with a site supervisor on location for the critical phases: structure alignment, first band, module installation start, calibration and handover. Local labor handles scaffolding, rigging support and general works under our supervision.

Tell Us Your Project

Send your venue drawings, dome diameter and content plan — our engineers reply within one business day with a tailored configuration.

Get a Free Quote